Home » Hai Long Offshore Wind Farm – Heavy Transportation

Hai Long Offshore Wind Farm - Heavy Transportation

Introduction

Hai Long 2 and 3 are being developed in Taiwan and is located 40-50km off the Changhua coast . Seaway7 were responsible for the transport of all jacket foundations fabricated at Samkang S&C Co. fabrication yard.

  • Project Hai Long 2 & 3 Offshore Wind Farms
  • Location Goseong, South Korea - Anping, Taiwan
  • Project Type Foundation Transportation
  • Assets Offshore heavy transportation was executed between March and November 2024 using Seaway 7’s heavy transport vessel Seaway Osprey.
  • Date Awarded August 2023
  • Completion Date November 2024

Project at a glance

In November 2020, Seaway Hawk arrived at the Port of Nigg, carrying her second load of ten jacket foundations from the UAE, for the Moray East Offshore Windfarm. This concluded a successful eight-month transportation campaign which utilised three of the company’s specialist heavy transport vessels, with Seaway Osprey, Seaway Albatross and Seaway Hawk working in rotation.

Seaway7 transported a total of 48 three-legged jackets from Lamprell’s Hamriyah fabrication yard to the Scottish installation port. The foundations averaged more than 1,000 tonnes in weight and 80m in height.

Highlights

  • Jacket foundations are the largest in deployment for offshore wind turbine, averaging 2,500 tonnes in weight and 93m in height.
  • Each of the 14 journey from Goseong to Anping, took an average of 4 days.
  • Seaway Osprey constantly sailed back and forth during the 7-month transportation campaign.

‘The jacket foundations are the largest in deployment for offshore wind turbines. We are very pleased to bring our extensive experience and proud to have played a key role in executing the transportation in a safe and efficient manner.’

Christophe Bregeon
Project Manager